grout and silicone

Grout & Silicone — Elegant Spaces
Quality Control · Photo Checklist
Grout & Silicone
填缝剂和硅胶
SiteCam Instructions · 操作说明
1
Open SiteCam and open the project — the project name is the site address
打开 SiteCam,选择对应项目 — 项目名称即为工地地址
2
Take your photos — you can take multiple photos at once, then press Done to go to the edit screen
拍摄照片 — 可连续拍摄多张,完成后点击「完成」进入编辑界面
3
On the edit screen — pin the group of photos to the correct room on the floor plan
在编辑界面 — 将这组照片标注到平面图上对应的房间位置
4
Set the record type to match the section you are working on — see each section below
记录类型设置为当前施工阶段 — 详见下方各分区说明
5
Pin to the floor plan, press Save then move on to the next item
标注到平面图,点击「保存」,然后继续下一项检查
Photos taken
0 / 14
Before 0/8 After 0/3 Materials 0/3
Complete
All photos taken — upload to SiteCam
Upload all photos before moving on to finish tiling
Before Grout & Silicone
填缝及打硅胶前
0/8
Capture all tiling details before grout goes on. Photo burst of each item, pin to the correct room on the floor plan. Record type: Tiling (before fit-off)
在填缝前拍摄所有铺贴细节。每项连拍多张照片,标注到平面图对应房间。记录类型:瓷砖施工(安装前)
01
Tiles laid level or plumb
拍照确认:瓷砖铺贴后保持水平或垂直。
02
Tiles laid with the correct fall in shower areas
拍照确认:淋浴区瓷砖坡度正确,水能顺利流向地漏。
03
Mitre cuts laid evenly with no chips in the tiles
拍照确认:瓷砖45°对角切角拼接整齐,没有崩边或缺口。
04
Trim clipped over the tile evenly
拍照确认:收边条已均匀扣在瓷砖边缘上。
05
Trim is flush with the tiles where water needs to flow — e.g. soap recess
拍照确认:在需要排水的位置(如肥皂凹槽),收边条与瓷砖齐平。
06
Key detail areas laid neatly — e.g. soap recess, feature strips
拍照确认:关键细节位置铺贴整齐 — 如肥皂凹槽、装饰条等。
07
Excess tile adhesive cleaned from the tiles
拍照确认:瓷砖表面的多余粘结剂已清理干净。
08
All joints clean and dust free — ready for grout
拍照确认:所有砖缝干净无灰尘 — 已准备好填缝。
After Grout & Silicone
填缝及打硅胶完成后
0/3
Photo burst of each item once grout and silicone is complete. Pin to the correct room on the floor plan. Record type: Grout & Silicone
填缝及打硅胶完成后,逐项连拍多张照片。标注到平面图对应房间。记录类型:填缝剂和硅胶
09
Epoxy grout mechanically mixed to correct ratios and being applied — grout evenly and fully filled with no gaps or voids
拍照确认:环氧填缝剂已按正确比例机械搅拌并正在施工 — 填缝均匀饱满,无空隙或缺口。
10
Grout residue fully removed and tiles polished — particularly important for epoxy grout
拍照确认:填缝残留物已完全清理干净,瓷砖已抛光 — 环氧填缝剂尤其重要。
11
Silicone applied neatly and to an even width, trim above showers siliconed, and silicone cleanly removed from all tile trims
拍照确认:硅胶打得整齐均匀,淋浴区上方收边条已打硅胶,所有收边条上的多余硅胶已整齐清理干净。
Materials & Site
材料及现场记录
0/3
Photo burst of each item, pin to the floor plan. Record type: Grout & Silicone
每项连拍多张照片,标注到平面图。记录类型:填缝剂和硅胶
12
Photo and description of all materials left on site
拍照记录现场所有剩余材料并说明品名及数量。
13
Materials needed to complete after fit-off set aside and ready — photo confirming enough adhesive, grout, silicone and trims to finish the job
拍照确认:完成安装后收尾所需材料已单独放置备用 — 确认瓷砖胶、填缝剂、硅胶及收边条数量足够完成剩余工作。
14
Work area left clean and tidy
拍照确认:施工区域已清理干净,保持整洁。