SiteCam Instructions · 操作说明
1
Open SiteCam and open the project — the project name is the site address
打开 SiteCam,选择对应项目 — 项目名称即为工地地址
2
Take your photos — you can take multiple photos at once, then press Done to go to the edit screen
拍摄照片 — 可连续拍摄多张,完成后点击「完成」进入编辑界面
3
On the edit screen — pin the group of photos to the correct room on the floor plan
在编辑界面 — 将这组照片标注到平面图上对应的房间位置
4
Set the record type to Waterproofing 1st Coat
将记录类型设置为「防水第一遍」
5
Pin to the floor plan, press Save then move on to the next item
标注到平面图,点击「保存」,然后继续下一项检查
Photos taken
0 / 4
Before 0/2
During 0/1
After 0/1
Before Starting Waterproofing
防水施工前
0/2
Take a photo burst of each item, then on the edit screen pin the group to the correct room on the floor plan. Set record type to Waterproofing 1st Coat and press Save.
每项连拍多张照片,在编辑界面将这组照片标注到平面图对应房间。记录类型选择「防水第一遍」后保存。
01
Screed is clean, dry and undamaged — photo burst to confirm
拍照确认:水泥找平层干净、干燥且无破损。
02
All substrates clean, dust free and primer applied — take multiple photos to capture all areas
拍照确认:所有基层干净、无灰尘,底涂已均匀涂刷完成 — 拍摄多张照片覆盖所有区域。
During Waterproofing — 1st Coat
防水第一遍施工中
0/1
Complete all detail work first. Then take a photo burst of every detail — close up and pulled back of the same detail. Group all detail photos and pin to the floor plan. Record type: Waterproofing 1st Coat
先完成所有细部处理。然后对每个细部连拍 — 包括特写和退后拍摄同一位置。将所有细部照片分组标注到平面图。记录类型:防水第一遍
03
All detail work complete — waterstops and RL80 bandage. Photo burst of all details close up and pulled back, then pin group to plan
所有细部处理完成 — 止水条及RL80加强带。对所有细部连拍特写及退后照片,将这组照片标注到平面图。
After Waterproofing 1st Coat
防水第一遍施工后
0/1
Take a photo burst of the completed first coat across all areas. Pin the group to each room on the floor plan. Record type: Waterproofing 1st Coat and press Save.
对所有区域第一遍防水完成面连拍多张照片。将这组照片分别标注到平面图各房间。记录类型:防水第一遍后保存。
04
Overall group photos of completed first coat — pin to plan
拍摄第一遍防水整体完工照片 — 标注到平面图。
11
Applied waterproofing is free from grit and debris
拍照确认:已施工的防水层表面干净,没有砂粒或杂物。