Waterproofing 2nd Coat
防水第二遍
SiteCam Instructions · 操作说明
1
Open SiteCam and open the project — the project name is the site address
打开 SiteCam,选择对应项目 — 项目名称即为工地地址
2
Take your photos — you can take multiple photos at once, then press Done to go to the edit screen
拍摄照片 — 可连续拍摄多张,完成后点击「完成」进入编辑界面
3
On the edit screen — pin the group of photos to the correct room on the floor plan
在编辑界面 — 将这组照片标注到平面图上对应的房间位置
4
Set the record type to match the section you are working on — see each section below
记录类型设置为当前施工阶段 — 详见下方各分区说明
5
Pin to the floor plan, press Save then move on to the next item
标注到平面图,点击「保存」,然后继续下一项检查
Photos taken
0 / 6
Before 0/1 After 0/4 Materials 0/1
Complete
All photos taken — waterproofing complete
Upload all photos to SiteCam before moving on
Before Starting 2nd Coat
第二遍防水施工前
0/1
Take a photo burst of all details — close up and pulled back of every internal corner, waterstop and penetration. Pin to the floor plan. Record type: Waterproofing 1st Coat
对所有细部连拍多张照片 — 包括每个内角、止水条及穿管处的特写和退后照片。标注到平面图。记录类型:防水第一遍
01
First coat completely dry including all corners — close up photos of all details, internal corners, waterstops and penetrations confirming no pin-holes. Pin to plan under Waterproofing 1st Coat
第一遍防水已完全干燥包括所有角落 — 对所有细部、内角、止水条及穿管处拍摄特写照片,确认无针孔。标注至平面图,记录类型选防水第一遍。
After Waterproofing 2nd Coat
防水第二遍施工后
0/5
Photo burst of each item, pin group to the correct room on the floor plan. Record type: Waterproofing 2nd Coat
每项连拍多张照片,将这组照片标注到平面图对应房间。记录类型:防水第二遍
02
Shower wall waterstops adhered to first coat with neutral silicone and RL80 bandage
拍照确认:淋浴墙面止水条已用中性硅胶粘贴于第一遍防水层上,并配合RL80加强带施工。
03
Thick coat of waterproofing applied to wall waterstops
拍照确认:墙面止水条处已涂刷厚实的防水层。
04
Overall photos of completed second coat — check for even thickness and no pin-holes as you take photos
拍照确认:防水第二遍整体完工照片,拍照时检查涂层厚度均匀、无针孔。
05
Work area left clean and tidy
拍照确认:施工区域已清理干净,保持整洁。
Materials Record
材料记录
0/1
Photo and description of all materials. Pin to the floor plan where materials are stored. Record type: Waterproofing 2nd Coat
拍照并说明所有材料情况。将照片标注到平面图上材料存放位置。记录类型:防水第二遍
06
Photo and description of materials left on site
拍照记录现场剩余材料并说明数量及品名。